Venable StormwaterDurham, NCProject Statistics:Project Type: Commercial Duration: 80 days Budget: $113,011 Square Footage: 1 Project TeamOwner: Scientific Properties Architect: Haden Stanziale General: C.T. Wilson Construction Co. Description:The Venable Stormwater project consisted of trenching a 24”storm sewer line across Roxboro Road in downtown Durham. The line connected the Venable storm sewer into a 60” main in Roxboro Road. The piping was installed one lane at a time due to the fact the road had to remain open for traffic flow. Existing utilities included electric lines, gas, water and data all had to be carefully worked around. |