Fidelity RTP Data Center

Morrisville, NC

Project Statistics:

Project Type:
   Commercial

Duration: 152 days

Budget: $892,665

Project Team

Owner: Fidelity Investments

Architect: Gilbane Building Co.

General: C.T. Wilson Construction Co.

Description:

The work consisted of renovating an existing building with data storage rooms, new access flooring for the computer rooms, new structural steel frames on the roof for the addition of numerous HVAC units and pumps to run the computer rooms. A new security system with card access was added. Miscellaneous special finishes including epoxy floors, new chillers, HVAC units and an extension to the mechanical court were installed.