UNC 3rd, 4th, & 5th Floor Renovation

Chapel Hill, NC

Project Statistics:

Project Type:
   Healthcare

Duration: 151 days

Budget: $379,110

Square Footage: 3,991

Project Team

Owner: UNC Hospitals

Architect: MHA Works

General: C.T. Wilson Construction Co.

Plumbing Contractor:Quality Mechanical Contractors

HVAC Contractor: Comfort Engineers

Electrical Contractor: DW Evans Electric, Inc.

Description:

This project consisted of renovating 3,991 square feet of hospital space. Construction included new Stretcher Area, Patient Bed Area, Recliner Area as well as support areas for staff. We coordinated complicated utility and system tie-ins to occupied floors above and below without significant interruption.