DRH OR 5 and 6

Durham, NC

Project Statistics:

Project Type:
   Healthcare

Duration: 280 days

Budget: $363,373

Square Footage: 800

Project Team

Owner: Duke University Medical Center

Architect: Roughton Nickelson De Luca Architect

General: C.T. Wilson Construction Co.

Plumbing Contractor: Brown Brothers Plumbing and Heating

HVAC Contractor: Hockaday Mechanical

Electrical Contractor: Pendergraph Electric

Description:

The project involved the renovation of two operating rooms to upgrade medical equipment. Operations were ongoing in adjacent rooms, so scheduling and cleanliness were critical aspects of this job.