UNC CT Scanner

Chapel Hill, NC

Project Statistics:

Project Type:
   Healthcare

Duration: 210 days

Budget: $444,471

Project Team

Owner: UNC Hospitals

Architect: MHA Works

General: C.T. Wilson Construction Co.

Plumbing Contractor:MFI Plumbing

HVAC Contractor: Comfort Engineers

Electrical Contractor: Watson Electric

Description:

This renovation project was divided into four phases in the basement of UNC Hospital. Area A converted existing Prep Area/Soiled Utility/Reading Room into two CT Scanner Rooms and a Control Room. Area B converted Offices/Toilet Room into a Reading Room. Area C converted a Dressing Room and Office into two Offices. Area D removed a Toilet Room and expanded a Control Room.