Gov. Mansion Renovation

Raleigh, NC

Project Statistics:

Project Type:
   Historic

Duration: 127 days

Budget: $5,613,434

Square Footage: 1

Project Team

Owner: State Construction Office

Architect: Sears, Hackney, Keener & Williams, Inc.

General: C.T. Wilson Construction Co.

Plumbing Contractor: Triangle Mechanical

HVAC Contractor: Environmental Air Systems

Electrical Contractor: Watson Electric

Description:

The Governor’s Mansion project was a mold remediation and renovation project. CT Wilson’s work included removal and replacement of the entire HVAC system, removing and replacing finishes, complete renovation of the basement and kitchen areas, installing new security, and installing systems to prevent the intrusion of moisture through the basement and other exterior areas. The project was carried out with a very limited schedule, which required long works hours seven days per week during much of the project. Design documents were issued as the project moved forward, and CT Wilson was directly involved in constructability and costing review. Close supervision was required to keep abreast of the latest scope additions and changes, and to ensure trades completed work properly and in a timely manner. C.T. Wilson took many special precautions to protect historic artwork and finishes during the project.

index.htm Client Area Employee Area Subcontractors Employment