Oncology Treatment CenterDurham, NCProject Statistics:Project Type: Healthcare Duration: 256 days Budget: $2,066,096 Square Footage: 10,000 Project TeamOwner: Duke University Medical Center Architect: Isley Hawkins Architecture General: C.T. Wilson Construction Co. Plumbing Contractor:Southern Piping HVAC Contractor: Southern Piping Co. Inc. Electrical Contractor: DW Evans Electric, Inc. Description:This was a four phase project. C.T. Wilson built extensive dust walls for the protection of chemotherapy patients during construction. All construction personnel wore protective suits to keep dust contained within the construction area. We installed temporary HVAC duct work to keep all patient areas conditioned during the construction. |