UNC Vascular RadiologyChapel Hill, NCProject Statistics:Project Type: Healthcare Duration: 359 days Budget: $1,754,452 Project TeamOwner: UNC Hospitals Architect: BJAC General: C.T. Wilson Construction Co. Plumbing Contractor:M & M Plumbing HVAC Contractor: Applied Controls Electrical Contractor: Process Power, Inc. Description:The Vascular Interventional Radiology Clinic continued operating within the site during construction. For this reason, the project was been divided into 3 main phases to avoid interrupting the active clinic. Each phase was completed in its entirety prior to the start of the next phase. Once the first phase was complete, the owner moved occupants of the next phase into the new space allowing the demolition to begin in the next phase. New space consists of two Procedure Rooms with lead radiation protection, equipment rooms, a doctor work room, patient exam rooms, prep/recovery rooms, nurse station, waiting area, lounge, reception area, checkout area and bathrooms. |